| Monday, April 17 |
Dry in roof, frame |
| Tuesday, April 18 |
Dry in roof, install windows / doors |
| Wednesday, April 19 |
Shingle and frame |
| Thursday, April 20 |
Shingle and install insulation |
| Friday, April 21 |
Shingle, hang drywall, paint |
| Saturday, April 22 |
Hang drywall, paint |
| Monday, April 24 |
Set cabinets |
| Tuesday, April 25 |
Clean floors and windows |
| Wednesday, April 26 |
Set interior doors |
| Thursday, April 27 |
Paint, tile floors, install closet shelves |
| Friday, April 28 |
Install shutters, baseboards, plant trees |
| Saturday, April 29 |
Final paint, lay sod |
|