| Monday, January 14 |
Dry in roof; Interior framing |
| Tuesday, January 15 |
Dry in roof; shingles; Install windows and doors |
| Wednesday, January 16 |
Roof shingles; framing |
| Thursday, January 17 |
Roof shingles; install insulation |
| Friday, January 18 |
Roof shingles; Hang drywall; Paint |
| Saturday, January 19 |
Hang drywall; Paint |
| Monday, January 21 |
Paint; Set cabinets; Clean floors |
| Tuesday, January 22 |
Finish cabinets; Install tiles, shutters, and mailboxes |
| Wednesday, January 23 |
Install doors, baseboards, bi-folds, and shelving; Clean porches |
| Thursday, January 24 |
NO VOLUNTEERS TODAY |
| Friday, January 25 |
Dig holes for plants and trees; Clean house & windows |
| Saturday, January 26 |
Landscaping; Clean & wax floor; DEDICATION
|
|